Borivali Infrastructure Pipeline 2026 to 2030: Projects and Timelines

Borivali's infrastructure pipeline for 2026 to 2030 includes six major projects that will reshape how you travel. The biggest is the Thane-Borivali Twin Tunnel, which will cut the Thane drive to about 15 minutes. Metro Line 9 to Mira-Bhayandar, the Dahisar-Bhayandar Link Road and new rail tracks to Virar follow close behind. The Goregaon-Mulund Link Road and the coastal road will also ease east-west and north-south travel by 2029.
| Project | What It Does | Status in 2026 | Target |
| Thane-Borivali Twin Tunnel | 11.8 km road tunnel to Thane under the national park | About 13% built by July 2026 | Around 2028, per reports |
| Metro Line 9 | Dahisar East to Mira-Bhayandar metro | First stretch opened April 2026 | Rest by December 2026 |
| Dahisar-Bhayandar Link Road | 5.1 km elevated road to Bhayandar | Piling under way, girders from October 2026 | December 2028 |
| Borivali-Virar 5th and 6th lines | Two new rail tracks for more local trains | Civil work at several stations | March 2028 |
| Goregaon-Mulund Link Road | 12.2 km east-west road with twin tunnels | Tunnel boring began September 2026 | 2029 |
| Coastal Road North | Versova to Bhayandar coastal route | Heavy work cleared in January 2026 | 2028 and beyond |